8/5/2024 - Announcement: Road open - Landslip repair works are complete with only the spray sealing works remaining. This final work is expected to be scheduled for late May, weather permitting, dates TBC. Council appreciates your patience as major landslip and road repair works near completion.
24/4/24 - Announcement: Road open Anzac Day Thursday 25 April 2024. Road closures and completion date are extended to Thursday 2 May 2024 following the impacts of 7 April 2024 severe weather and flooding event (AGRN 1119). Find details under - About the works.
Council appreciates your patience as major landslip and road repair works near completion.
17/4/2024 - Announcement: Road open Anzac Day Thursday 25 April 2024. Road closures - due to the impacts of declared natural disaster 7 April (AGRN1119) severe weather and flooding event, road closures and completion date are extended to Tuesday 30 April 2024. Find details under - About the works. Council appreciates your patience as major landslip and road repair works near completion.
10/4/2024 - Announcement: Road closures. Due to the impacts of the 7 April declared natural disaster (AGRN1119) storm event, road closures and completion date are extended to 30 April 2024. Find details under - About the works. Council appreciates your patience as major landslip and road repair works near completion.
3/4/2024 - Announcement: Completion date is revised to Tuesday 16 April 2024, weather permitting, due to designers' delayed advice.
26/3/2024 - Announcement: Road open over Easter weekend. From Good Friday 29 March to Easter Monday 1 April 2024, Foremans Road will be open and repair works will be shut down. Repair works resume Tuesday 2 April 2024. Council appreciates your patience and extends good will for a safe Easter weekend.
12/3/2024 - Announcement: Closure extension. Contractor Symal has advised that due to wet ground conditions planned road closures are extended to 10 April 2024. Full road closures Mondays to Saturdays, 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller. Find more details under - About the works.
27/2/2024 - Announcement: Closures extended. Contractor Symal advised that planned road closures and expected completion is extended to 26 March 2024, due to recent wet weather conditions. Full road closures Mondays to Saturdays, 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller. Council appreciates your patience and extends good will for a safe 2024.
The latest: Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'.
20/2/2024 - Recent wet weather conditions have extended the expected completion date to 7 March 2024. Full road closures planned through to 7 March 2024, Mondays to Saturdays 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller during closure times.
From 2/1/7/2024 to 23/2/2024 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page weekly under ‘Related Documents’. Repair works and road closures were also detailed weekly for all sites under ‘About the works’.