The Shoalhaven was declared a Natural Disaster Area 22 February (AGRN 1012), 27 June (AGRN 1025) and 14 September (AGRN 1034), all severe weather and flooding events. Recorded infrastructure damages totaled 1347, the total damage bill estimate is $85 million.
Wide ranging damages to infrastructure included landslips, flood levee's, jetties, boat ramps, beach stairs, bridges, roads (sealed & unsealed), culverts, footpaths, storm water (sink holes), roadside furniture and emergency works. Council successfully secured funding to repair wide ranging damages, including 38 major landslips across 15 roads for the Major Landslip Package.
Below: Damages on Woodhill Mountain Road required immediate clean-up works.
![An excavator works to remove a large boulder and landslide debris covering a road.](/files/content/public/v/182/council/projects-and-works/major-projects/natural-disaster-reconstruction-works/woodhill-landslip.jpg?w=862&h=550)
Find information on natural disaster road repair and reconstruction works on our Natural Disaster Repair Works Listings page.
The Major Landslip Package
Council's Natural Disasters Team has championed this project to completion, collaborating and working closely with the contractor Symal, Public Works Authority (PWA) and council teams.
Some challenges overcome during these works include providing adequate access for community during works, effectively communicating road closures to community and during the final stages of completion works absorbing the impacts of three (3) more natural disasters; 28 November 2023 (AGRN 1086), 7 April 2024 (AGRN 1119), and 6 June 2024 (AGRN 1129).
All fully completed and reconstructed landslips in the package withstood the latter three (3) severe weather events, proving the completed and repaired major landslips robust in the face of extreme weather events. A defining test of the completed works.
The latest
15/7/2024 - Finishing off works on Foremans Road, Woodhill, are in progress while the final landslip in this repair package on Bunkers Hill Road, Barrengarry, is due for completion 10 September 2024.
20/6/2024 - Final works have been disrupted and delayed on Bunkers Hill Road, Burrier Road, Foremans Road and Wattamolla Road by two (2) recent natural disaster events, 6 June and 7 April 2024. However, finishing works are in progress as favourable weather conditions prevail.
16/05/2024 - Repair works near completion on the final four roads; Bunkers Hill Road (5), Burrier Road (5), Foremans Road (2), Wattamolla Road (3).
Major landslip reconstruction works (38 landslips) are completed on: Abernethys Road, Bamarang Road (2), Browns Mountain Road, Hughes Road (2), Kangaroo Valley Road (2), Mount Scanzi Road (8), Suffolk Road, Upper Kangaroo River Road (4), Wogamia Road, Woodhill Mountain Road (2) and Yalwal Road.
Council and contractor Symal are working diligently for completion of the Major Landslip Package for mid-2024, weather permitting. To date, they have delivered a robust result.