Severe weather events reconstruction work - 2022

Information on local reconstruction works caused by the 2022 natural disasters.

 
Woodhill Mountain Road landslip
 
  • Project StatusIn progress
  • Last reviewed 23 March 2023

The latest

3/3/2023 - The construction program outlining the planned start and finish dates for the 38 Major Landslip repair work has been released.
See Major Landslip Repairs below for more information.

About the project

Information on your local road can be found on Council’s road works page.

The July 2022 east coast low natural disaster event brought with it torrential rain, damaging winds and floods that resulted in widespread landslips, road damage and isolation for some in our community.

The Shoalhaven community showed incredible resilience again following the March 2022 natural disaster event that brought more heavy and sustained rainfall that caused further widespread damage to our public infrastructure and impacted many in our community.

The September 2022 severe weather and floods was also declared natural disaster but mainly caused widespread damage to communities in western NSW. This same weather event also impacted the Shoalhaven LGA although the damage to our infrastructure and the impacts to our community this time was much milder.

On this page

 

Background

For the months of January to July 2022, rainfall in Barrengarry alone reached a total of 2,059mm (see related documents) compared to an average rainfall for the same period of 854mm and was more than double the rainfall what residents would normally experience. This follows two summers of La Niña weather patterns with a third La Niña expected over the 2022/23 summer expecting to bring more heavy rainfall and flooding. 

During this time 3 severe weather events were declared natural disasters by the NSW Government:

  • AGRN1012 – NSW severe weather and flooding from 22 February 2022 onwards
  • AGRN1025 – NSW severe weather and flooding from 27 June 2022 onwards

The impacts on public infrastructure were significant, including:

  • 1200 records of damage and emergency works across the Shoalhaven
  • an estimated $75 million in damaged roads
  • an estimated $4 million in damage to flood levees
  • 98 landslips (38 classified as major) affecting 23 roads
  • 13 sinkholes

The estimated cost to repair the damage is nearly 4 times the value of Council's normal roads and transport annual capital work construction program budget. To respond to this challenge, Council set up a dedicated natural disaster reconstruction team to focus on the repair work.

The above data is as of July 2022. For updated data see Ordinary Council Meeting reports in Related Documents. 

The severe weather and floods in September 2022 were also declared natural disaster.

  • AGRN1034 – NSW severe weather and flooding from 14 September 2022 onwards

 

Natural Disaster Funding Arrangements 

As both severe weather events have been recognised as natural disasters, Council is eligible for federal funding to restore essential infrastructure under strict conditions outlined in

Under these funding arrangements, Council is seeking funding under Category B measures for ‘restoration of essential public assets’. There are three distinct stages of restoration works: 

Stages of Restoration Works

Stage 1 (emergency work) - Completed

Removal of debris to allow restricted traffic movement.

Load limits (refer below) and traffic management have been imposed on some roads around the region to improve driver safety and prevent further road damage.

Stage 2 (immediate reconstruction work) - Completed

In certain locations, significant repair work has been completed to improve public safety and restore property access for residents.

See related documents for a list of the immediate reconstruction works completed to date.

Stage 3 (essential public asset reconstruction work) - In Progress

Stage 3 involves the investigation, design and construction of the initial 38 high priority landslip repairs impacting roads is a large undertaking and planning for this work is well underway.

Planning for the lower priority works, including initial investigation, recommendations and concept designs, will commence early November 2022 and will follow a similar process to the higher priority works.

 

Major Landslip Repairs (Stage 3)

3/3/2023 - The latest construction program proposed by the contractor Symal for the 38 the Major Landslip repair work has been released and is available in the related documents on this page.  See "Major Landslip Package Program March 2023".

A summary of this construction program is also shown below by clicking on the heading "Major Landslip Package Planned Program of Work”

21/2/2023 - As previously reported, Council resolved on the 15th February 2023 to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips affecting 15 of Shoalhaven Council’s roads. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works expected to begin in late March 2023.

This week Council project management team will be meeting with the contractor to confirm planned dates when individual landslip repairs will commence. This project master page and the 15 individual roadworks pages will be updated to provide the planned commencement dates for the 38 landslip repairs as soon as these dates are confirmed. You can view the list of major landslips and the assigned construction priorities by clicking on the heading “Major landslip package priorities” below. 

14/02/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities below. 

22/12/2022 - Four tenders for the repair of 38 landslips were received. A comprehensive evaluation process has been completed and a recommendation has been forwarded to Public Work Advisory (PWA) for endorsement. It is anticipated that PWA will evaluate the tender acceptance report and respond to Council mid-January.

Previous Progress Updates

15/12/2022 - Tender Process for the Landslip packages is progressing well.

The current status of the Landslip Tender is as follows

  • Council has received four bids in the tender box.
  • Non-price evaluation is complete with promising proposals from experienced contractors.
  • Price evaluation is nearing completion with final checks and balances being considered for each submission.
  • Project references and financial checks on each of the bidders is currently underway.
  • After the above checks, direct discussions with preferred tenderers will be undertaken.
  • Based upon evaluation to date we are confident that the tender process will result in an award of the works.
  • From review of the submissions both options A and B as per Councils strategy are real possibilities under consideration.
  • Prior to the Christmas break the evaluation team is confident that the process will be complete with reports sent for endorsement.

31/10/2022 - The investigation, design and construction of the initial 38 high priority major landslip repairs impacting roads is a large undertaking and planning for this major program of work is well underway.

Geo-technical consultants, SLR Consulting P/L, have been engaged to undertake the detailed investigation and design of the landslip repair work of the 38 high priority sites. The investigation and drilling work is now complete as well as the environmental due diligence assessment and preliminary cost estimates. Design work has now reached 85%.

With assistance from the NSW Public Works Advisory, tender documents for the 38 high priority works were completed and issued for public tender on 31 October 2022 and closed on 6 December 2022. 

eTendering - Current Tender Detail View - RFT-10053781 (nsw.gov.au) 

The extensive tender evaluation process is likely to take several weeks depending on the quantity and quality of the tenders submitted. Prior to Council accepting any tender, Council has an obligation to seek final endorsement from the NSW Public Works Advisory regarding the preferred tender, as well as endorsement from TfNSW who approves the final scope of work, the allocation of Natural Disaster funds and verifies compliance with the NSW Disaster Assistance Arrangements.

Allowing for the Christmas shutdown period, a tender for the 38 major land slip repair work is likely to be accepted in late January 2023 which will allow Council to enter into a construction contract.

Depending on the time it takes for the contractor to mobilise equipment, staff and to procure materials it is now most likely repair will commence in March 2023.

Project-Delivery-Time-frame-2.png 

 


Major Landslip Package Planned Program of Work

Location

District

Rural Address (approx)

Road

Chainage

(kms)

Planned Start

Planned Finish

Bunkers Hill Rd

Northern

159

1.580-1.600

10-May-23

29-Jun-23

Bunkers Hill Rd

Northern

175

1.720-1.780

16-May-23

29-Jun-23

Bunkers Hill Rd

Northern

183

1.800-1.860

23-May-23

29-Jun-23

Bunkers Hill Rd

Northern

212

2.080-2.160

27-Jun-23

18-Oct-23

Bunkers Hill Rd

Northern

394

3.900-3.980

27-Jul-23

17-Oct-23

Upper Kangaroo River Rd

Northern

676

6.720-6.800

18-Apr-23

31-Aug-23

Upper Kangaroo River Rd

Northern

691

6.880-6.940

18-Jul-23

31-Aug-23

Upper Kangaroo River Rd

Northern

755

7.520-7.580

04-Aug-23

31-Aug-23

Upper Kangaroo River Rd

Northern

1291

12.900-12.920

08-Aug-23

31-Aug-23

Burrier Rd

Central

730

0.540-0.920

10-May-23

07-Aug-23

Burrier Rd

Central

377

3.640-3.900

14-Jun-23

07-Aug-23

Burrier Rd

Central

333

3.320-3.340

18-Jul-23

07-Aug-23

Burrier Rd

Central

610

5.780-6.420

16-May-23

08-Aug-23

Woodhill Mountain Rd

Northern

552

5.420-5.620

11-May-23

16-Jun-23

Woodhill Mountain Rd

Northern

570

5.640-5.760

17-May-23

30-Jun-23

Foremans Rd

Northern

43

0.370-0.490

24-May-23

08-Aug-23

Foremans Rd

Northern

32

0.280-0.360

03-Jul-23

08-Aug-23

Kangaroo Valley Rd

Northern

1260

12.6

07-Aug-23

11-Aug-23

Kangaroo Valley Rd

Northern

1167

11.660-11.680

11-Aug-23

31-Aug-23

Mount Scanzi Rd

Northern

823

8.220 - 8.240

28-Jun-23

21-Jul-23

Mount Scanzi Rd

Northern

794

7.900-7.980

11-Jul-23

06-Sep-23

Mount Scanzi Rd

Northern

779

7.760-7.820

19-Jul-23

06-Sep-23

Mount Scanzi Rd

Northern

777

7.760-7.780

24-Jul-23

06-Sep-23

Mount Scanzi Rd

Northern

771

7.700-7.720

01-Aug-23

06-Sep-23

Mount Scanzi Rd

Northern

657

6.560-6.580

09-Aug-23

15-Aug-23

Mount Scanzi Rd

Northern

587

5.840-5.900

15-Aug-23

06-Sep-23

Mount Scanzi Rd

Northern

588

5.88

28-Aug-23

28-Aug-23

Suffolk Road

Basin

48

0.420-0.540

31-Jul-23

16-Aug-23

Wattamolla Rd

Northern

13

0.10-0.1600

29-Aug-23

08-Nov-23

Wattamolla Rd

Northern

356

3.56

22-Sep-23

09-Oct-23

Hughes Rd

Northern

199

1.980-2.000

06-Sep-23

26-Sep-23

Hughes Rd

Northern

197

1.960-1.980

12-Sep-23

05-Oct-23

Browns Mountain Rd

Northern

364

3.630-3.650

15-Aug-23

08-Sep-23

Wogamia Rd

Central

98

0.940-1.020

26-Sep-23

20-Oct-23

Abernathys Rd

Northern

191

1.900-1.920

29-Aug-23

19-Sep-23

Bamarang Rd

Central

325

3.240-3.360

12-Oct-23

23-Nov-23

Bamarang Rd

Central

319

3.180-3.200

01-Nov-23

23-Nov-23

Yalwal Rd

Central

957

9.56-9.60

07-Nov-23

20-Nov-23

 

Moderate Landslip Repair Package

Location

Rural address No. (approx)

Browns Mountain Rd 296
Browns Mountain Rd 282
Browns Mountain Rd 286
Bunkers Hill Rd 194
Emerys Rd 19
Greville Av TBA
Greville Av 150
Hughes Rd 222
Hughes Rd 154
Kangaroo Valley Rd 228
Kangaroo Valley Rd 1162
Kangaroo Valley Rd 116
Kangaroo Valley Rd 1246
Kangaroo Valley Rd 230
Kangaroo Valley Rd 1168
Matron Porter Dr TBA
Mt Scanzi Rd 792
Mt Scanzi Rd 800
Mt Scanzi Rd 824
Mt Scanzi Rd 782
Mt Scanzi Rd 636
Mt Scanzi Rd 692
Tourist Rd TBA
Tourist Rd 26
Upper Kangaroo River 1260
Wattamolla Rd 388
Wattamolla Rd 366
Wattamolla Rd 404
Wattamolla Rd 396
Wattamolla Rd 311
Wattamolla Rd 402
Wattamolla Rd 666

 

Completed & Upcoming Road Works (Stage 3)

The information below provides an overview of the roads impacted by the natural disasters and tender information for each district. 

Request for Tender timelines are unfortunately delayed. Council is awaiting approval from TfNSW and NSW Reconstruction. Individual project pages will be updated as soon as confirmation is received. 

To see more detailed information regarding the individual road works, use the links in All Works and subscribe to remain updated. 

Northern District

Completed Pavement

Rehabilitation 

Upcoming Pavement

Rehabilitation  

  • Elliotts Ln, Meroo Meadow (unsealed)
  • Schofields Ln, Berry (unsealed)
  • Irvines Rd, Berry Mountain (unsealed)
  • Jacks Corner Rd, Kangaroo Valley (unsealed) 
  • Woodhill Mt Rd, Woodhill (sealed patch before slip)
  • Budgong Rd, Budgong (unsealed)  

 Unsealed Roads:

  • Abernethys Rd, Budgong

 

 Round 1: 

 Geotechnical investigations underway.  Request for Tender to be issued March 2023

  • Illaroo Rd, North Nowra
  • Hockeys Ln, Cambewarra
  • Jacks Corner Rd, Kangaroo Valley 
  • Coolangatta Rd, Coolangatta

 

 Round 2 & 3:

 Work being scoped. Request for Tender to be issued mid-March 2023. 

  • Kangaroo Valley Rd, Berry Mountain
  • Hillandale Rd, Broughton Vale
  • Agars Ln, Berry
  • Main Rd, Cambewarra
  • Gerroa Rd, Coolangatta
  • Irvines Rd, Berry Mountain 

Central District

Completed Pavement

Rehabilitation 

 Upcoming Pavement

Rehabilitation 

 Round 1:

  • Cabbage Tree Lane, Nowra Hill
  • Callala Beach Rd, Callala Beach
  • Culburra Rd, Wollumboola
  • Jindy Andy Lane, Pyree
  • Worrigee Rd, Worrigee 

 Round 2:

  • Greenwell Point Rd, Brundee
  • South St & Comerong Island Rd, Terara    

 Round 3:

 Geotechnical advice being sought. Round 3 Request for Tender to be called February 2023:

  • Terara Road, Terara
  • Commerong Island Road, Numbaa
  • Millbank Road, Terara
  • Burrier Road, Barringella
  • Yalwal Road, West Nowra
  • Culburra Rd, Wollumboola

Basin District

 Completed Pavement

Rehabilitation

 Upcoming Pavement

Rehabilitation

 Round 1:

  • The Wool Road, Basin View
  • Naval College Road, Basin View
  • Evelyn Road, Basin View
  • Jervis Bay Road, Jervis Bay
  • Roper Street, Vincentia
  • Pine Forest Road, Tomerong
  • Murray Street, Vincentia
  • Woollamia Road, Falls Creek

 Round 2: 

 Round 2 Contract awarded. Work commences Jan 2023.

  • Cammaray Dr, St Georges Basin
  • Tilbrook Av, St Georges Basin
  • Albion St, Sanctuary Point

 

 Round 3: 

 Finalising scope. Request for Tender to be issued Feb 2023. 

  • Braidwood Rd, Sassafras
  • Jervis Bay Road, Falls Creek
  • Turpentine Rd, Tomerong
  • Dowling Street, Falls Creek

Southern District

 Completed Pavement   

Rehabilitation 

Upcoming Pavement

Rehabilitation

  

 Round 1:

 Geotechnical advice is being engaged. Request for Tender to be issued in March 2023.

  • Woodstock Rd, Woodstock
  • Lake Conjola Entrance Rd, Yatte Yattah
  • Sussex Inlet Rd, Tullarwalla
  • Fisherman’s Paradise Rd /Alma Av, Fisherman’s Paradise
  • Inyadda Dr, Manyana
  • Bendalong Rd, Bendalong

 

All Works

Status Location District Last updated Road status Restrictions
done 1 Albion Street, Sanctuary Point 2540 13 March 2023
Open
done 4 Cammaray Drive, St Georges Basin 2540 20 March 2023
Closed
done Abernethys Road, Budgong 2577 Northern 16 March 2023
Open
3 tonne
done Abernethys Road, Budgong 2577 Northern 02 March 2023
Open
Load limit
3 tonne
done Agars Lane, Berry 2535 02 March 2023
Open
done Bamarang Road, Bamarang 2540 Central 04 March 2023
Open
done Barfield Rd, Cambewarra 2541 Northern 09 March 2023
Open
done Beach street, Huskisson 2540 Basin 19 December 2022
Open
done Bendalong road, Bendalong 2539 16 March 2023
Open
Reduced speed
done Braidwood Road, Tianjara 2622 Basin 21 February 2023
Open
One way
done Braidwood Road, Sassafras 2622 Basin 14 March 2023
Open
Reduced speed
Road damage
done Browns Mountain Road, Browns Mountain 2540 Northern 16 March 2023
Open
done Bryces Rd, Far Meadow 2535 Northern 09 March 2023
Open
No restrictions
done Bunkers Hill Road, Barrengarry 2577 16 March 2023
Closed
Load limit
5 tonne
Residents only
done Burrier Road, Burrier 2540 Central 19 January 2023
Open
Reduced speed
done Burrier Road, Burrier 2540 Central 04 March 2023
Open
Reduced speed
Traffic lights
done Cabbage Tree Lane, Nowra Hill 2540 18 November 2022
Open
done Callala Beach Road, Callala Beach 2540 18 November 2022
Open
done Comerong Island, Terara 2540 Central 02 March 2023
Open
No restrictions
done Coolangatta Road, Coolangatta 2535 Northern 23 March 2023
Open
Reduced speed
done Croziers Road, Jaspers Brush 2535 Northern 23 March 2023
Open
12 tonne
done Culburra Rd, Wollumboola 2540 19 January 2023
Open
done Dowling Street, Falls Creek 2540 24 February 2023
Open
done Duffys Lane, Budgong 2577 Northern 13 February 2023
Open
done Evelyn Rd, Tomerong 2540 18 November 2022
Open
done Fishermans Paradise Road, Fishermans Paradise 2539 Southern 09 February 2023
Open
done Foremans Road, Woodhill 2535 16 March 2023
Closed
Load limit
5 tonne
Residents only
done Gerroa Road, Coolangatta 2540 Northern 02 March 2023
Open
Road damage
done Greenwell Point Road, Worrigee 2540 Central 17 March 2023
Open
done Hillandale Road, Broughton Vale 2535 Northern 03 March 2023
Open
done Hockeys Lane, Tapitallee 2540 Northern 23 March 2023
Open
done Hughes Road, Illaroo 2540 Northern 16 March 2023
Open
done Illaroo Road, North Nowra 2540 23 March 2023
Open
Reduced speed
done Irvines Rd, Berry Mountain 2540 Northern 02 March 2023
Open
done Island Point Road, St Georges Basin 2540 Basin 02 March 2023
Closed
done Jacks Corner, Kangaroo Valley 2577 Northern 23 March 2023
Open
done Jervis Bay Road, Falls Creek 2540 07 February 2023
Open
done Jindy Andy Lane, Pyree 2540 18 November 2022
Open
done Kangaroo Valley, Berry Mountain 2535 Northern 02 March 2023
Open
done Kangaroo Valley Road, Kangaroo Valley 2577 Northern 16 March 2023
Open
Load limit
12 tonne
Reduced speed
done Lake Conjola Entrance Road, Yatte Yattah 2577 Southern 09 February 2023
Open
done Main road, Cambewarra Village 2540 Northern 02 March 2023
Open
done Martinvale Road, Jaspers Brush 2535 Northern 23 March 2023
Open
done McMahons Rd, North Nowra 2541 Northern 09 March 2023
Open
No restrictions
done Millbank Road, Terara 2540 Central 16 February 2023
Open
done Mount Agony Road, Durras North 2539 Southern 13 March 2023
Open
done Mt Scanzi Road, Kangaroo Valley 2577 Northern 16 March 2023
Open
One lane
done Murray St - Vincentia, Vincentia 2540 18 November 2022
Open
done Naval College Road, Worrowing Heights 2540 10 March 2023
Open
done Old Burrier Road, Burrier 2540 Central 17 March 2023
Open
done Penguins head road, Culburra Beach 2540 Central 16 February 2023
Open
done Pine Forest Road, Tomerong 2540 01 February 2023
Open
done Porters Creek Road, Pointer Mountain 2539 Southern 22 March 2023
Open
done Roper St - Vincentia, Vincentia 2540 18 November 2022
Open
done Roskell road, Callala Beach 2540 Central 17 March 2023
Open
done Schofields Lane, Berry 2540 Northern 21 December 2022
Open
done Scott St, Shoalhaven Heads 2540 Northern 21 March 2023
Closed
Road damage
done Suffolk Road, Tomerong 2540 Basin 04 March 2023
Open
One lane
Residents only
done Sussex Inlet Road, Tullarwalla 2577 Southern 09 February 2023
Open
done Terara Road, Terara 2540 Central 17 March 2023
Open
done The Wool Road, Basin View 2540 15 March 2023
Open
No restrictions
done Tilbrook Avenue, St Georges Basin 2540 20 March 2023
Open
done Tourist Road, Beaumont 2577 22 November 2022
Open
done Turpentine Road, Tomerong 2540 Basin 24 February 2023
Open
Reduced speed
Road damage
done Upper Kangaroo River Road, Upper Kangaroo River 2577 16 March 2023
Closed
9 tonne
Residents only
done Wattamolla Road, Wattamolla 2535 Northern 07 February 2023
Open
Load limit
9 tonne
done Wattamolla Road, Woodhill 2535 Northern 16 March 2023
Open
Load limit
9 tonne
done Wogamia Road, Longreach 2540 Central 04 March 2023
Open
Road damage
done Woodburn Road, 2538 Southern 13 March 2023
Open
Reduced speed
done Woodhill Mountain Road, Woodhill 2535 Northern 16 March 2023
Open
One lane
Reduced speed
Traffic lights
done Woodstock road, Morton 2538 Southern 13 March 2023
Open
Reduced speed
done Woollamia Rd, Falls Creek 2540 18 November 2022
Open
done Yalwal Road, Yalwal 2540 Central 04 March 2023
Open
Road damage
done Yalwal Road, Mundamia 2540 Central 17 March 2023
Open
Gravel

 

Interim Slip Repairs – Completed (Stage 2 )

The following land slip, interim works have completed under Stage 2 (immediate reconstruction works), to allow restricted traffic access under strict load limits:

  • Wattamolla Rd – two locations
  • Upper Kangaroo River Rd – two locations
  • Foremans Rd
  • Woodhill Mountain Rd
  • Suffolk Rd 

Current Road Load Limits

The following roads have strict load limits imposed for public safety:

Address

Dry Weather Load Limit

At 136 Bunkers Hill Rd, Kangaroo Valley

 5 tonne– resident access only, closed to other traffic

 24/7 load & traffic restriction enforcement in place

At 368B Bunkers Hill Rd, Kangaroo Valley

 Closed to all traffic. New cracks in roadway detected

At 40 Foremans Rd, Kangaroo Valley

  5 tonne – resident access only, closed to other traffic

Wattamolla Rd, Woodhill Mountain

 9 tonne, entire length

 24/7 load & traffic restriction enforcement in place

At 685 Upper Kangaroo River Road, Upper Kangaroo River

 9 tonne – resident access only, closed to other traffic

 24/7 load & traffic restriction enforcement in place

 Kangaroo Valley Road, Kangaroo Valley  12 tonne
 Abernethys Rd, Budgong  3 tonne
 Crozier Rd, Jaspers Brush  12 tonne

 

The imposed road load limits at various slip sites have been confirmed by Council’s geotechnical consultants by applying slope stability analysis. This considers vehicle loads, geology, soil conditions and road embankment slopes to derive a factor of safety against further embankment collapse.

Refer related documents for more information.

Vehicle Weight Limit Exemption Application

Council road management staff will consider requests for an exemption to a load limit at a landslip site, and this can be done by downloading and completing the SCC Application Form – Load Limit Exemption.

Any consideration of a temporary load limit exemption would be on a risk assessment of slope stability undertaken by Council’s geotechnical consultant.

Allow at least 10 business days to have this application considered.

Road Closures - Trigger Action Response Plan (TARP)

This TARP assists us to manage existing and historical land slip sites based on predicted rainfall events. 

Roads currently affected with load limits imposed due to landslips can deteriorate and slip further due to further heavy rainfall. Council has trigger points when deciding to close a road to all traffic for safety reasons:

Predicted rainfall in

24-hour period

Council Action

 Less than 50mm

 

  •  Manage road as if under “Dry Conditions” with daily inspections.
  • Should new tension cracks or edge slumps appear, or increase, the road will be closed at the landslip site and reopened pending engineering advice.
 Between 50mm and 100mm
  • Continue to manage road as if under “Dry Conditions” with increased frequency of inspections.
  • If new tension cracks or edge slumps appear, or increase, the road will be closed at the landslip site and reopened pending engineering advice.
 Above 100mm
  • CLOSE ROAD (just before rain commences)
  • Inspection to occur only when rain has stopped.
  • The road is only re-opened after surface water has dissipated and no further rain is imminent.
  • If new tension cracks or edge slumps appear, or increase, the road will remain closed and only be reopened pending engineering advice.

 

The nature of the landslip hazard is such that in most cases it is not possible to give notice of a road closure before a road closure is implemented. Council understands the impact that a road closure can have on residents and the Community and only implement such measures in the face of imminent hazardous conditions.

Storm and Flood Customer Care Service

supporting image

If you have been affected by the March or July 2022 severe storms and floods, there are a range of assistance measures that may be available to support you.