23/5/2024 - Stage one of repair works, patches on Bendalong Road, were bitumen sealed Wednesday 22 May 2024. Please reduce speed and follow aftercare speed restrictions as repaired sections are yet to be line marked. Council’s contractor returns mid next week to stabilise works on remaining Bendalong Rd patches before starting repairs on Inyadda Dr.
15/5/2024 - Announcement: Reduce speed & drive to conditions. Day and night traffic control is in place to Monday 13 May 2024. Pilot vehicles will escort vehicles though the site, one direction at a time. The contractor is monitoring the site over the weekend. Please reduce speed and drive to conditions. Road works are on hold and will start again when the weather permits. Subscribe to this page for updates.
10/5/2024 - Drive to conditions. Bendalong Rd has been impacted by ongoing wet weather this week. With unsealed sections of road and potential for conditions to deteriorate, please reduce speed and drive to conditions. Roadworks have been impacted by ongoing rain and are on hold. Roadworks will start again when weather permits.
7/5/202 - Announcement: Drive to conditions. Bendalong Rd has been impacted by ongoing wet weather this week. With unsealed sections of road and potential for conditions to deteriorate, please reduce speed and drive to conditions.
Repair works on hold. Due to the ongoing heavy rainfall repair works on Bendalong Rd are on hold. Repair works will start again when the weather permits. Subscribe to this page for updates
19/4/2024 - Announcement: Pavement repair works have started. Works will be carried out under traffic control; minor delays may be experienced. Works are expected to take four (4) weeks to complete, weather permitting.
2/4/2024 - Announcement: Repair works to start. Contractor Roadworx has scheduled necessary pavement repair works to start Monday 15 April 2024. Works will be carried out under traffic control; minor delays may be experienced. Repair works are expected to take 4 weeks to complete, weather permitting.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence mid-April 2024. Works are expected to take 4 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.
16/02/2024 - Road works on Bendalong Road are expected to commence in April 2024.