7/5/202 - Announcement: Drive to conditions. Bendalong Rd has been impacted by ongoing wet weather this week. With unsealed sections of road and potential for conditions to deteriorate, please reduce speed and drive to conditions.
Repair works on hold. Due to the ongoing heavy rainfall repair works on Bendalong Rd are on hold. Repair works will start again when the weather permits. Subscribe to this page for updates
19/4/2024 - Announcement: Pavement repair works have started. Works will be carried out under traffic control; minor delays may be experienced. Works are expected to take four (4) weeks to complete, weather permitting.
2/4/2024 - Announcement: Repair works to start. Contractor Roadworx has scheduled necessary pavement repair works to start Monday 15 April 2024. Works will be carried out under traffic control; minor delays may be experienced. Repair works are expected to take 4 weeks to complete, weather permitting.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence mid-April 2024. Works are expected to take 4 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.
16/02/2024 - Road works on Bendalong Road are expected to commence in April 2024.