27/2/2024 - Announcement: Works ahead of schedule. Contractor Symal has advised works at Site 4 are progressing ahead of schedule with an anticipated completion date of 26 July 2024. Extra equipment and resources have been mobilised to advance completion of repair works. For details see media release 16 February 2024, under About the works.
Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'.
20/2/2024 - Announcement: Contractor Symal has advised works at Site 4 near rural address 610 are progressing ahead of schedule. The expected completion date is now 26 July (no longer 30 August) 2024. Night closures are ongoing.
From 2/1/7/2024 to 19/2/2024 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page weekly under ‘Related Documents’. Repair works and road closures were also detailed weekly for all sites under ‘About the works’.
Repair works progressing steadily
Above: Site 4 landslip repairs progressing well February 2024.
Above: Site 4 in progress October 2023.
Above: Site 3 repair works are well underway.
Above: Site 1 landslip repair works nearing completion.