Package 1: Stage 1 water main lead-in work (completed 2021)
- Package 1 works completed 2021
Package 2: Illaroo Road water pumping station upgrade (anticipated completion April 2024)
- Testing and commissioning of the new pump station is currently underway, with the new pumps now switched on
- Fencing and access road pavements have now been installed/commenced
- Coming up:
-
- The decommissioning and demolition of the existing pump station
- Completion of facility fencing
- Landscaping works
Package 3: Stage 2 water mains (anticipated completion May 2024)
- Main Road, Hockeys Lane and Faulks Place: Nearing completion! Final fittings, connections, and testing are expected to be finalized within the coming days.
- Reservoir Lane: Pipeline installation is complete. Testing and commissioning are likely the next steps.
- Moss Vale Road (Badagarang): Progressing steadily! The section under the Jemena gas line is now bored and pipes are installed. Work continues on the pipeline running between Taylors Lane and the final Bomaderry connection point.
Package 4: New water reservoir Cambewarra
- Construction works are progressing well with main structure now complete, reservoir being filled and external batters and access road pavement underway