  • Project Status

The Moss Vale Road (MVR) Urban Release Area (URA) is a regionally significant residential development located between Bomaderry and Cambewarra village. The current projected development yield is 3,400 residential lots. In order to supply adequate future servicing to the URA, Shoalhaven Water is currently progressing Wastewater infrastructure.

Overall Project Highlights:

  • Project Approval 2020
  • Award of design consultants – 2020
  • Completion of Moss Vale Road wastewater infrastructure detailed design – December 2021
  • Award of wastewater infrastructure construction contractor – December 2021

The Works

  • Package 1: Moss Vale Road Southern (MVRS) Urban Release Area (URA) Wastewater Infrastructure
  • Construction of new sewer pumpstation (SPS) to MVRS
  • Construction of new sewer gravity and raising mains
  • Package 2: MVR URA – Sewer Pumping Stations
  • Construction of new sewer pumping stations to Moss Vale Road Northern (MVRN) Urban Release Area (URA) and Illaroo Road (SPS21)
  • Construction of new sewer gravity and rising mains
  • Package 3: MVR URA – Pipelines

Construction of new sewer gravity and rising mains connecting the MVR URAs to the existing Bomaderry Wastewater Treatment Plant (WWTP).

Critical Works

Works have commenced within Lot 15 DP 1286870, 63 Emerald Drive, Meroo Meadow. The works include an underbore drill from the Western side of the Princes Highway within Lot 601 DP 1223625, 15 Abernethys Lane to Lot 15 DP 1286870, 63 Emerald Drive per the below sketch plan (refer green line for approx. location, with underbore drill extent between the red lines as indicated).

Moss Vale wastewater.png

The construction site within Lot 15 DP 1286870, 63 Emerald Drive is specifically for the underbore drill of the Princes Highway only and the site setup and large structures are temporary only. At the completion of the works, it will simply entail an inground pipeline with associated small above ground air valve.

Underbore drilling works are anticipated to continue for an additional 3-4 week period, subject to weather conditions and other construction efficiencies; though the project team are working hard to fast track the current underbore drilling works to minimise any ongoing impacts.

Shoalhaven City Council has defined specific timeframes for the underbore Contractor to undertake the drilling works. Due to the criticality of the underbore drill, difficulties in construction, and to reduce the overall timeframe of the works, Shoalhaven City Council has agreed to the following working hours:

  • Works on Weekdays (Monday to Friday) permitted between 7am-6pm.
  • Works on Saturdays permitted between 7am-5pm.
  • No works on Sundays.
  • Work on Public Holidays permitted between 7am-5pm.

August - September 2022 Update

  • Package 1: Moss Vale Road Southern (MVRS) Urban Release Area URA Wastewater (WW) Infrastructure
    • MVRS rising main installed
    • MVR Southern URA gravity trunk main installed
    • MVRS sewer pump station (SPS) construction and installation commenced
  • Package 2: Moss Vale Road (MVR) – Sewer Pumping Stations (SPS)
    • MVRN SPS access road continued
    • MVRN SPS property settlement completed
  • Package 3: Moss Vale Road (MVR) Urban Release Area (URA) – Pipelines
    • MVRS gravity trunk main installation continued
    • MVRS rising main installed
    • SPS23 rising main diversion continued
    • MVRN rising main installation continued
    • MVRN rising main highway under bore works commenced    

MV1.png