Foremans Road - Woodhill - Major Landslips (2)

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and rain events. This had a major impact on Kangaroo Valley and surrounding communities, landslips affecting roads and property. Foremans Road, Woodhill, was severely impacted by these rain events. Immediate works were carried out to remove debris, clearing the road for traffic movement as soon as possible.

The latest

Select image to view Site 1 landslip near completion

About the works

Landslip repair sites

Site 1 DM00882 - rural address 43 and Site 2 DM00555 - rural address 32 - completed. 

Site 1 and Site 2 major landslip repairs in progress 23 May 2024

foremans latest 1 - Adam - 23May24.jpg foremans latest - Adam - 23May24.jpg

This project was part of the Major Landslip Package 2022, delivery of 38 fully remediated landslips across 15 roads, with final completion November 2024. Council thanks residents for their patience and understanding through the delivery of this critical project. This project was jointly funded by the Australian Government and NSW Government under the Disaster Recovery Funding Arrangements. 

2024 Works history

16/7/2024 - AnnouncementForemans Road is open. Final repair works and completion date will be advised when drainage design is confirmed. Updates will be provided here. Council appreciates your patience as final works progress to completion.

9/7/2024 - AnnouncementForemans Road is open. Sealing works are postponed due to damaged pavement from foundation water. An updated drainage design is pending approval. Updates will be provided here. Council appreciates your patience as final works progress to completion.

29/5/2024 - Temporary ClosureFull road closure for final trim and swale works planned from Monday 27 May to Monday 3 June 2024, weather permitting, Monday to Friday. Full closure Monday to Friday 7.30am to 4.30pm, no vehicle access. Pedestrian access only with traffic control escort during closures. For details see - About the works. Council appreciates your patience as major landslip and road repair works near completion.

15/5/2024 - AnnouncementPlanned closures 28 to 31 May 2024 for spray sealing works are yet to be confirmed (TBC). Subscribe to this page for updates. Landslip repair works are complete with only the spray sealing works anticipated in late May. Council appreciates your patience as major landslip and road repair works near completion.

8/5/2024 - Announcement: Road open - Landslip repair works are complete with only the spray sealing works remaining. This final work is expected to be scheduled for late May, weather permitting, dates TBC. Council appreciates your patience as major landslip and road repair works near completion.

24/4/24 - Announcement: Road open Anzac Day Thursday 25 April 2024. Road closures and completion date are extended to Thursday 2 May 2024 following the impacts of 7 April 2024 severe weather and flooding event (AGRN 1119). Find details under - About the works.

17/4/2024 - Announcement: Road open Anzac Day Thursday 25 April 2024. Road closures - due to the impacts of declared natural disaster 7 April (AGRN1119) severe weather and flooding event, road closures and completion date are extended to Tuesday 30 April 2024. Find details under - About the works. Council appreciates your patience as major landslip and road repair works near completion.

10/4/2024 - Announcement: Road closures. Due to the impacts of the 7 April declared natural disaster (AGRN1119) storm event, road closures and completion date are extended to 30 April 2024. Find details under - About the works. Council appreciates your patience as major landslip and road repair works near completion.

3/4/2024 - Announcement: Completion date is revised to Tuesday 16 April 2024, weather permitting, due to designers' delayed advice.

26/3/2024 - Announcement: Road open over Easter weekend. From Good Friday 29 March to Easter Monday 1 April 2024, Foremans Road will be open and repair works will be shut down. Repair works resume Tuesday 2 April 2024. Council appreciates your patience and extends good will for a safe Easter weekend.

Site 1 and Site 2 major landslip repair works in progress 13 March 2024

FOREMANS RD DM00882 Site 1 - Adam - 13Mar24.jpg  FOREMANS RD DM00555 site 2 - Adam - 13Mar24.jpg

12/3/2024 - AnnouncementClosure extension. Contractor Symal has advised that due to wet ground conditions planned road closures are extended to 10 April 2024. Full road closures Mondays to Saturdays, 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller. Find more details under - About the works. 

27/2/2024 - Announcement: Closures extended. Contractor Symal advised that planned road closures and expected completion is extended to 26 March 2024, due to recent wet weather conditions. Full road closures Mondays to Saturdays, 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller. Council appreciates your patience and extends good will for a safe 2024.

The latest: Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'. 

20/2/2024 - Recent wet weather conditions have extended the expected completion date to 7 March 2024. Full road closures planned through to 7 March 2024, Mondays to Saturdays 7.30am to 4.30pm. No vehicle access during closures, pedestrian access via escort by Traffic Controller during closure times.

From 2/1/7/2024 to 23/2/2024 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page weekly under ‘Related Documents’. Repair works and road closures were also detailed weekly for all sites under ‘About the works’. 

 

2023 Works history

Site established with repair works in progress

foremans rd 1609.jpg

From 09/08/2023 to 22/12/2023 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page by council weekly, under ‘Related Information’. Repair works progress and road closures were also detailed weekly for all sites under ‘About the works’.

08/08/2023 - Site 1. DM00882 Works start Wednesday 11 October through to Thursday 26 October 2023. Site 2. DM00555 Works start Friday 27 October through to Friday 17 November.

21/06/2023 - Contractor Symal releases revised construction program. See 'Construction Program - Remediation - Multiple slips - Shoalhaven' under Related Information.

30/03/2023 - Landslip design plan for Foremans Road is attached. Located under - Related Documents

30/03/2023 - Landslip repair drop-in sessions: Thu 30 March 4 – 5pm Thu 13 April 4 – 5pm. Drop by the Kangaroo Valley Hall (177 Moss Vale Rd) where Symal and Council will answer your questions about upcoming roadworks.

17/03/2023 - Kangaroo Valley Information Session on Friday 17 March, 7pm - 8pm (followed by BBQ) at KV Community Hall. Meet contractor Symal and get briefing on the start of landslip works.

04/03/2023 - The latest construction program proposed by contractor Symal for the 38 the Major Landslip repair work has been released. The construction program lists the planned start and finish date for each of the 38 land slips. A summary of the construction program is available on the  Major Landslip Package Planned Program of Work. A copy of the construction program is also available on the right-hand side of the Master Project Page in the related documents section.

15/2/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities on the Master Project Page

 

2022 Works history

3/11/2022 - Following months of geotechnical investigations, design work and tender preparation, Council is now seeking contractors to bid on the 38 landslips deemed a priority. Submissions close 6 December 2022. Shoalhaven Area – Remediation of Multiple Slips – RFT – 10053781.

16/10/2022 - Pothole patching Thursday 27th October 2022. Resident access and restrictions apply only from mailbox 40Maintaining road safety and access across the city remains Council's highest priority and Council is working hard to fast track the repair work at the site and thus increase/remove the load limits as soon as possible. Please see the below definition of “Residents Only”.

14/10/2022 - Resident access and restrictions apply only from mailbox 40Maintaining road safety and access across the city remains Council's highest priority and Council is working hard to fast track the repair work at the site and thus increase/remove the load limits as soon as possible. The current load limit on this road is 5Tonne.Please see the below definition of “Residents Only”.

6/10/2022 - With rainfall forecast for the Shoalhaven, Council reminds residents that it may become necessary to close access roads previously impacted by land slips. The trigger is 40mm of rain within any 24-hour period. Council will provide as much warning as possible should this occurs. Maintaining road safety and access across the city remains Council's highest priority. Load limit on this road is 3Tonne

22/09/2022 - Following record rain events, Council has recorded 98 landslides as a high priority, with a focus on 35 sites that are deemed most urgent. We've now finished geotechnical investigations at these 35 sites, leading the way for designs to be completed in the coming weeks. The designs form part of a works package that will go out to tender in October. Load limit on this road is 3Tonne

16/09/2022 - Geotechnical engineers will be conducting a site investigation on Foremans Road, from Friday 9th September 2022. The road will be open during the investigation. Borehole drilling will be conducted to inform the design.

02/09/2022 - Foremans Road is now open with the completion of the interim repair of the landslip. The road will re-open with an increased road limit of 3Tonne.

17/08/2022 - Advising, Foremans Road will be closed tomorrow, Thursday 18 August, from 9.30am to 12.30pm to finalise the temporary repair at the landslip. The road closure will allow contractors to apply the final seal. Once the seal has been installed the road will re-open with an increased road limit of 3tonne.

16/08/2022 - Foremans Road is now open for residents only, with a 2-tonne load limit. Geotechnical engineers will review the site today and assess the need for repairs before opening the road to all traffic.

12/08/2022 - Foremans Road closure on Friday 12 August. This Friday our geotechnical engineers are carrying out work to address the hazardous road surface. To allow engineers to safely stabilise the site with erosion protection material (Geocell) the road needs to be closed between 8 am and 3 pm. We appreciate residents understanding and will update you if the weather impacts the closure.

05/08/2022 - Foremans Road, Woodhill - Open. While the road has opened again after the removal of debris please be aware that wet weather may result in the road being slippery with hazardous material on the road surface. Please drive to the conditions of the road. Soil reinforcement and erosion protection material (Geocell) and pavement will be installed from Monday to fix the issue.

04/08/2022 - Foremans Road, Woodhill  - closed Hazardous road conditions have led to the closure of the Road today and tomorrow. While the road is expected to be reopened to local traffic on the weekend, please be aware that wet weather may result in the road remaining closed. Soil reinforcement and erosion protection material (Geocell) and pavement will be installed on Monday to fix the issue.

The design has now been finalised for the preferred solution to reinstate appropriate access to Foremans Rd. The works will involve a realignment to the existing roadway. Works will start 1st August 2022 and are expected to take approximately 3 weeks to be completed weather permitting. The road will be close intermittently during the works under traffic control.

pic foremans beorn 26072022.PNG

04/07/2022 - Investigations are ongoing.

16/06/2022 - Restrictions remain in place while Geotechnical investigation works continue.09/06/2022 - Council is reviewing recommendations from the initial geotechnical investigations. Restrictions remain in place with traffic being limited to residents only.

02/06/2022 - Design work continues. Restrictions remain in place with traffic being limited to residents only.

26/05/2022 - Geotechnical investigations have been completed.