Callala Beach Rd - Callala Beach - Pavement Repair
Pavement repair
- Public access
Open
No restrictions
- Where
Callala Beach Road, Callala Beach 2540
- Project StatusCompleted
- Last reviewed
31 March 2023
The latest
Pavement repair on Callala Beach Road is complete including line marking.
About the works
06/10/2022 - Pavement works under the external tender package have been completed. Line marking remains outstanding.
![Callala beach Rd SA00009.JPG](/files/content/public/v/15/council/projects-and-works/road-works/callala-beach-rd-callala-beach-pavement-repair/callala-beach-rd-sa00009.jpg?w=1011&h=658)
16/09/2022 - Asphalt repair work will continue on Monday 19th September weather permitting. A single lane will operate under traffic control during this time. Council advises that residents should allow for extra travel time.
08/09/2022 - Asphalt repair work will commence Friday 09/09/2022, and will continue for approximately 5 days weather permitting. A single lane will operate under traffic control during this time. Council advises that residents should allow for extra travel time
20/08/2022 - Contractors due to commence Tuesday 23rd August. Central AC program scheduled for a 4 week construction period.
![callala beach rd.JPG](/files/content/public/v/15/council/projects-and-works/road-works/callala-beach-rd-callala-beach-pavement-repair/callala-beach-rd.jpg?w=1003&h=628)