Culburra Road - Wollumboola - Pavement Repair
The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and subsequent rain events. This had a major impact on our communities, causing rapid deterioration to pavements and roads. Culburra Road, Wollumboola, was severely impacted by these rain events.
Pavement repairs:
Section 1. Completed
Section 2. Planning
- Public access
Open
No restrictions
- Where
Culburra Rd, Wollumboola 2540
- Project StatusPlanning
- Last reviewed
09 May 2024
The latest
9/5/2024 - The last update is still the most current for this repair work. Further updates will be provided as new information becomes available. Subscribe to this page for updates.
16/11/23 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Tenders are ready for advertising pending TfNSW approval.
About the works
2024 Works history
04/03/24 - The last update is still the most current for these repair works.
2023 Works history
- 16/11/23 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Tenders are ready for advertising pending TfNSW approval.
- 05/09/2023 - Maintenance staff are undertaking weekly inspection of the road and actioning temporary road repairs as required.
- 06/04/2023 - Maintenance staff will undertake weekly inspection of the road and schedule temporary pothole repairs as required.
- 29/03/2023 - Temporary pavement repairs are being completed at this location prior to Easter (pothole repairs and large shoves).
- 24/03/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Tenders are ready for advertising pending TfNSW approval.
- 19/01/2023 - Sampling and testing investigations have commenced to inform appropriate repair methods. Once completed Council will seek funding approval from transport to proceed to tender the works.
- 18/01/2023 - Additional pavement repair works will be undertaken with sampling and testing commencing in January 2023. An external package of works will go to tender in February 2023.
2022 Works history
Section 1 - Complete
- 18/11/2022 - All works under the external tender package have been completed.
- 31/10/2022 - A contractor has been engaged to reinstate the line marking that was removed during pavement repairs. Works are scheduled for mid-November, weather permitting.
- 22/10/2022 - A request for quote has been sent to suitable line marking contractors. Quotes are expected to be received by 28th October, with works to be undertaken in November.
- 15/09/2022 - Pavement works under the external tender package have been completed. Line marking remains outstanding.
- 16/08/2022 - Contractors due to commence Tuesday 23rd August. Central AC program scheduled for 4-week construction period.
Jump to subscribe
Location
-34.934352, 150.692198
Culburra Rd ,
Wollumboola 2540
Culburra Rd ,
Wollumboola 2540