01/11/2023 - Works to complete the pipe culvert and construct a retaining wall are nearing completion.
Final restoration works are being carried out over the next week.
21/09/2023 - Works to replace the pipe culvert and construct a retaining wall is progressing and is expected to take six (6) weeks to complete. A temporary side road has been constructed to allow traffic around the site.
29/08/2023 - Council has awarded the works. Council's contractor is planning to begin works from 4 September 2023. The works to replace the pipe culvert and construct a retaining wall is expected to take 6 weeks to complete. A temporary side road will be constructed to allow traffic around the site.
28/07/2023 - Works have been Tendered to replace the failed pipe culvert and construct a gabion outlet structure. Construction will commence once the successful contractor is awarded the works.
07/06/2023 - The works for replacing the failed pipe culvert and constructing a gabion outlet structure have been tendered. Once the tender process has been finalised, construction will commence.
16/05/2023 - A design to replace the failed pipe culverts and construct a gabion outlet structure have been approved by Transport NSW. Staff are currently preparing documentation to Tender the works for construction.
02/03/2023 - Further investigations of the site have been carried out and survey and design works are being undertaken for the repair works. Construction works will follow once the design is finalised and approved by Transport NSW.
19/01/2023 - Request for quotations to replace the failed pipe culvert have been sent. Works will be carried out following assessment of quotations.