1/9/2024 - Pavement repair works are complete. Minor works and site clean-up to be fully completed by Friday 6 September 2024.
15/8/2024 - Pavement repair works are underway and are anticipated to be completed by Friday 23 August 2024, weather permitting.
25/07/2024 - Pavement repair works are scheduled by the contractor to start late July 2024. Works are expected to take 3.5 weeks to complete, weather permitting.
8/7/2024 - The last update is current. Updates will be provided as new information becomes available.
18/6/2024 - Pavement repair works are rescheduled by the contractor to start in late July 2024. Rescheduled start date is due to ongoing rain events. Works are expected to take 3.5 weeks to complete, weather permitting.
03/06/2024 - Pavement repair works are scheduled by the contractor to commence early July 2024. Works are expected to take 3.5 weeks to complete, weather permitting.
07/05/2024 - Pavement repair works are scheduled by the contractor to start mid-June 2024. Works are expected to take 3.5 weeks to complete, weather permitting. Subscribe to this page for updates.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence early June 2024. Works are expected to take 3.5 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.