1/9/2024 - The contractor is currently undertaking pavement defect rectification works which are expected to be completed by Friday 6 September 2024.
25/07/2024 - Pavement repair works are complete; however, Councils' contractor will be returning to site end of August 2024 to rectify pavement defects.
05/07/2024 - Pavement repair works are complete. The contractor has rescheduled returning to site for mid-July to rectify some pavement defects.
18/06/2024 - Pavement repair works are complete. The contractor has rescheduled returning to site for early July 2024 to rectify some pavement defects.
03/06/2024 - Pavement repair works are complete; however, the contractor is expected to be returning to site in coming weeks to rectify some pavement defects.
07/05/2024 - Pavement repair works are complete. Line marking work will be carried out in the coming weeks.
19/04/2024 - Pavement repair works are nearing completion, with final seal being carried out today. Line marking of the repairs will be done in the coming weeks.
2/4/2024 - Announcement: Repair works to start. Contractor Roadworx has scheduled necessary pavement repair works to start Monday 8 April 2024. Works will be carried out under traffic control; minor delays may be experienced. Repair works are expected to take 2 weeks to complete, weather permitting.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence early April 2024. Works are expected to take 2 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.