Inyadda Drive - Manyana - Pavement repair

The Shoalhaven was declared a Natural Disaster Area after the March 2022 East Coast Low and subsequent rain events caused extensive damage to many Council assets. Inyadda Drive, Manyana, was severely impacted and extensive road repair works are planned.

The latest

1/9/2024 - Pavement repair works are completed - select image.

About the works

Pavement repair works are fully completed August 2024

INYADDA DRIVE - pavement completion 1 - Will - Aug24.jpeg

2024 Works history

Pavement repair work is progressing to completion

INYADDA DRIVE - completion - Adam - 8Jul24.jpg

16/8/2024 - Pavement repair works are complete, and line marking will be completed in late August 2024, weather permitting.

25/7/2024 - Pavement repair works are scheduled to be completed by end of July 2024. Line marking is scheduled to be completed mid-August, weather permitting.

05/07/2024 - Pavement repair works are nearing completion. Line marking anticipated to be completed mid-July 2024, weather permitting.

03/06/2024 - Pavement repair works are rescheduled by the contractor to commence mid-June 2024.

07/05/2024 - Due to recent weather events, pavement repair works are rescheduled by the contractor to start late in May 2024.

05/03/2024 - Pavement repair works are scheduled by the contractor to commence late April 2024.

29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.

 

2023 Works history

Road deterioration from severe weather events 2022

Inyadda Dr - original damage - Mar2022 - Reflect .jpg

15/11/2023 - Tender is expected to be awarded in December 2023 with works commencing in early 2024.

 