Holden Street - Vincentia - Footpath Repair

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and subsequent rain events. This had a major impact on our communities, causing rapid deterioration to pavements and roads. Holden Street, Vincentia was impacted by these events. Council has works approval to repair the undermined footpath behind Elizabeth Drive, between Church Street and Holden Street.

The latest

19/02/2024 - Works on the undermined pathway are now complete. Sediment control barriers will remain in place until the area stabilises.

About the works

2023 Works history

  • 14/02/2024 - Work on the undermined footpath has commenced and is expected to take two weeks, weather permitting. During this time, the footpath will be closed to the public between Church St and the raised footbridge. A detour will be available either on the beach or via Holden St, Elizabeth Dr and Church St.
  • 10/01/2024 - To minimise disruption during the holiday period, work on the undermined footpath will now commence in early February 2024, weather permitting.
  • 05/12/2023 - Due to adverse weather conditions, rectification works will now be undertaken week commencing 12 December, weather permitting. Works are expected to take approximately two weeks.
  • 18/10/2023 - Council will undertake rectification works week commencing 27 November, weather permitting. Works are expected to take approximately two weeks.
  • 19/09/2023 - Council is still in the process of obtaining environmental permits in order to rectify the damage and is hoping to commence work in early November 2023, weather permitting.
  • 19/07/2023 - Council is still in the process of obtaining environmental permits in order to rectify the damage but is hoping to commence work in mid to late August 2023, weather permitting.
  • 03/07/2023 - Council is still in the process of obtaining environmental permits in order to rectify the damage. A commencement date for the work will be determined once permits are granted.
  • 15/06/2023 - Council is in the process of obtaining environmental permits in order to rectify the damage. Work is due to commence 3 July 2023 with a completion date of 14 July 2023, weather permitting.
  • 06/06/2023 - Council is in the process of obtaining environmental permits in order to rectify the damage. Work is due to commence 19 June 2023 with a completion date of 30 June 2023, weather permitting.
  • 24/05/2023 - Rectification of the undermined footpath behind Elizabeth Drive, between Church Street and Holden Street, is due to commence 19 June 2023 with a completion date of 30 June 2023, weather permitting.
  • 12/05/2023 - Rectification of the undermined footpath behind Elizabeth Drive, between Church Street and Holden Street, is due to commence mid June 2023.  Works are expected to take approximately 2 weeks, weather permitting.
  • 20/04/2023 - Rectification works are due to commence on 22 May 2023.  Works are expected to take approximately 1 week, weather permitting.

 

Jump to subscribe