16/11/23 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Tenders are ready for advertising pending TfNSW approval.
05/09/2023 - Maintenance staff are undertaking weekly inspection of the road and actioning temporary road repairs as required.
31/05/2023 - Maintenance staff are undertaking weekly inspection of the road and actioning temporary road repairs as required.
06/04/2023 - Maintenance staff will undertake weekly inspection of the road and schedule temporary pothole repairs as required.
29/03/2023 - Temporary pavement repairs are being completed at this location prior to Easter (pothole repairs and large shoves).
24/03/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Tenders are ready for advertising pending TfNSW approval.
02/03/2023 - South Street: Major damaged section has been repair and works completed. Additional damages have been identified for repair. Sampling and testing investigations are currently being reviewed and submitted for Transport for NSW funding approval.
16/01/2023 - South Street: Works to commence on 18th January 2023 with works taking 7 days weather dependent.