Update 09/06/2023: The road closure has now been lifted.

The Plunkett Street road closure is managed by Transport for NSW (TfNSW) in association with the development of a food establishment by Spectrum Retail Group. 

Timelines

  • The full road closure allows works to occur between 14 April and 1 July
  • Original estimates stated the project would take 11 weeks to complete
  • Current estimates are closer to 8 weeks
  • It is anticipated that works will be finished in June 2023

Works

Road works are required to make sure that:

  • Entering and exiting from the development is safe
  • Access to the highway is properly integrated
  • The local road network continues to operate at a suitable level of service and safety

If you have any further questions, Transport for NSW can be contacted at their Wollongong Regional Office on 1800 049 961, or you can contact the project manager for Spectrum Retail, Vaughan Reddell, directly on 0427 177 783.