Worrigee Road /Isa Rd to east watercourse - Nowra

Installation of drainage pits and pipes from Isa Road intersection through to watercourse to the east.

  • Public access
    open
  • No restrictions
  • Where Worriegee Road, Nowra 2541
  • Estimated completion date02 December 2022
  • Project StatusCompleted
  • Last reviewed 23 February 2023

The latest

Restoration works are completed.

About the works

Latest updates

 

  • 28/11/2022 - Restoration works are continuing
  • 01/09/2022 - Project Nearing completion.
  • 08/08/2022 - Delayed due to wet weather and flooding.
Jump to subscribe