Western Distributor Road - Currowan - Crossing Upgrade

A piped culvert crossing on Western Distributor Road over Currowan Creek is being upgraded to a bridge to improve fish passage.

The latest

May 2025 Update - The design phase of the contract is complete. Material procurement and pre-works documentation is in progress. Construction is scheduled to commence mid-June 2025. Refer to the notification of works letter for further details.

About the works

This bridge infrastructure project was identified and is being funded by Department of Regional NSW – DPI Fisheries under the Marine Estate Management Strategy (MEMS) program.

The existing culvert crossing on Currowan Creek at Western Distributor Road is being upgraded to a bridge to improve fish passage.  

Estimated Project Timeline:

  • Preliminaries & Project Tendering - Late 2024
  • Contract Award - Early 2025
  • Design Phase of the Contract - February to May 2025
  • Construction Phase of the Contract - June to September 2025

Please subscribe to stay updated on this project. 

History

  • April 2025 Update - The contract has been awarded. The design phase of the contract is in progress. Construction is scheduled to commence mid-June 2025. Refer to the notification of works letter for further details.
  • March 2025 Update - The contract has been awarded. The design phase of the contract has commenced. Construction is scheduled to commence mid-June 2025.
  • January 2025 Update - Tender evaluation in progress.
  • November 2024 Update - Tender submissions are due 19 December 2024.
  • October 2024 Update - The project will be tendered in November 2024 as a Design and Construct contract.
  • January 2024 Update - Preliminaries including Review of Environmental Factors in progress.

 