Council has received funding through the Disaster Recovery Funding Arrangements to carry out rehabilitation works on Wattamolla Road at CH6220.
- Public access
open
No restrictions
- Where
Wattamolla Road, Kangaroo Valley 2577
- Estimated completion date16 May 2025
- Project StatusPlanning
- Last reviewed
08 May 2025
The latest
05/05/2025 - Pre-construction works are in the final stages. Contractors are scheduled to commence works on Monday, 12th May 2025. The expected completion date is Friday, 16th May 2025. Traffic control measures will be in place, and delays could be expected.
About the works
Repair of headwall and pavement damaged from Disaster event, June 2024. Pavement surface damaged and shoulder scoured on tight corner near 638 Wattamolla Rd. Road will be open under traffic control.