21/12/2023 - A contract to undertake pavement repairs has been awarded. Works are scheduled to commence mid-late January 2024. Please expect changes to traffic conditions and possible delays.
01/11/2023 - Pavement repair works have been tendered for construction. Following the tender process, works are expected to commence early 2024.
18/08/2023 -Transport NSW have approved the repair methodology for the pavement reconstruction works.
25/05/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.
06/04/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.
28/03/2023 - Northern Maintenance Roads Crew are undertaken pothole repairs on Coolangatta Road this week Tuesday 28 March to Friday 31 March, weather permitting. Traffic control is in place so please plan for delays.
23/03/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.
19/01/2023 - Council has submitted request to Transport NSW to approve the repair method before works can be tendered for Construction.
19/01/2023 - Geotechnical Investigations for pavement repairs have been carried out to inform appropriate repair methods. Council is currently waiting for Transport NSW to approve the repair method before works can be Tendered for Construction. A temporary 60km/h speed zone and pothole warning signs have been installed to inform motorists of the condition of the road.