16/03/2026 - Council’s contractor is currently coordinating service relocations works with the various communications asset owners prior to establishing on site for construction.
10/02/2026 - Construction works have been awarded to A1 Earthworx Mining & Civil Pty Ltd t/a Cleary Bros. Construction planning and procurement is underway, and works are expected to start onsite early March 2026 with a completion date of end of August 2026.
21/01/2026 - Tenders for the project have closed and are being reported to Council at its meeting on 27 January 2026 where a contractor will be selected to undertake the works.
28/11/2025 - The Project is currently out for Tender.
17/10/2025 - Design Documents have been finalised, and tender documents for construction are currently being prepared.
21/07/2025 - A geotechnical investigation is currently underway to validate the pavement design.