A review of the existing sewerage systems has identified a need to upgrade the Huskisson/Vincentia SPS 7 rising main, gravity main and emergency storage.
Portion 1 - The sewer rising main has been installed between Vincentia WWTP and McNamara Court.Portion 2 - Power pole on Montague Street installed in December 2024.Portion 3 - Construction works of the sewer gravity mains between Montague Street and McNamara Court and the upgrade of SPS 7 on Montague Street is planned to commence in mid 2026.
Shoalhaven Water, as part of their asset management practices, has decided to upgrade and replace the sewer rising main, gravity main, and pump station in Montague Street, McNamara Street, and Berry Street Vincentia.
Detailed designs have been completed for the upgrades to the rising main and gravity main at Sewer Pumping Station (SPS) 7 on Montague Street.
These upgrades are necessary to handle increased wastewater flows, improve efficiency, and reduce the risk of wastewater overflows into the environment. A Review of Environmental Factors (REF) report was publicly exhibited in November 2023.
The detailed designs comprised of three distinct portions as follows:
The REF was prepared in March 2023 and was publicly exhibited and endorsed in November 2023
D24-525035-SW-75268E-Huskisson-SPS-7-IMG_7958-min.jpg
D24-525036-SW-75268E-Huskisson-SPS-7-IMG_8010-min.jpg
D24-525052-SW-75268E-Huskisson-SPS-7-IMG_8544-min.jpg
D24-525080-SW-75268E-Huskisson-SPS-7-IMG_8007-min.jpg
Berry Street , Vincentia 2540