Construction of a 2.0m wide footpath on the eastern side of Dolphin Point Rd running from the Burrill Lake Lions Park access road to Seaside Parade. The project also includes kerb & gutter construction and drainage improvements.
Council has received the Aboriginal Heritage Impact Permit (AHIP) for Stage 2 (the northern section) of the pathway at Dolphin Point Road. Construction of Stage 2 is planned to commence from 01 February 2027.
October 2026 Update - Council has received the Aboriginal Heritage Impact Permit (AHIP) for Stage 2 of the Dolphin Point Rd pathway (northern section). Several permit conditions must be met before work can begin. To allow time to satisfy these requirements and avoid major roadworks over Christmas and New Year, construction is planned to commence from 1 February 2027 and take approx. 3 months.
Staging-for-project-page-Dolphin-Point-Path_1.png
Dolphin-Point-Tree-Clearing.jpg
Footing-for-retaining-wall-Dolphin-Point.jpg
Dolphin-Point-Rd-Footpath-Retaining-Wall.jpg
Dolphin-Point-Basecourse-top-of-hill.jpg
Dolphin-Point-Basecourse-bottom-of-hill-2.jpg
Dolphin-Point-Rd-Footpath-Pour-at-Top-of-Hill-1.jpg
Dolphin-Point-Rd-Footpath-Pour-at-Top-of-Hill-2.jpg
Dolphin-Point-Rd-Footpath-Pour-at-Bottom-of-Hill.jpg
Dolphin-Point-Footpath-Asphalt-done-road-open-1.jpg
Dolphin-Point-Footpath-Asphalt-done-road-open-2.jpg
Dolphin-Point-Footpath-Handrail-installed.jpg
Council has gained NSW Government funding to complete the Dolphin Point Road footpath as part of the election commitment to support active transport in the Shoalhaven region.
Refer to the related information section to view the latest design.
August 2026 Update - Stage 1 works are complete. Stage 2 construction is pending the outcome of the Aboriginal Heritage Impact Permit process. Stage 2 timing TBC.
July 2026 Update - Stage 1 works are complete. Stage 2 construction is pending the outcome of the Aboriginal Heritage Impact Permit process. Stage 2 timing TBC.
June 2026 Update - Stage 1 works are complete. Stage 2 construction is pending the outcome of the Aboriginal Heritage Impact Permit process. Stage 2 timing TBC.
April 2026 Update - Stage 1 works are complete. Stage 2 construction is pending the outcome of the Aboriginal Heritage Impact Permit process. Stage 2 timing TBC.
26/02/2026 Update - Asphalt is complete. Road has been reopened to traffic. Footpath is open for use. Planting in progress. Handrail to be installed next week.
12/02/2026 Update - All of Stage 1 footpath has been completed. Road works continuing into next week. Seal date TBC.
29/01/2026 Update - Footpath has been poured from Bonnie Troon Cl to the roundabout. Remainder of footpath to be completed by mid-next week. Road set to be sealed at the end of next week, weather permitting.
15/01/2026 Update - Works are continuing. A stormwater road crossing will be constructed early next week with the road set to be sealed at the end of next week, weather permitting.
23/12/2025 - Despite the best efforts of the Contractor to get the road back to two lanes prior to Christmas, the road will continue to operate under mobile traffic lights over the break with the Contractor set to complete the road works early in January.
December 2025 Update - Construction of the retaining wall is complete. Backfilling behind the retaining wall and reconstruction of the road is continuing. The project is on track to have the road back to two lanes over the Christmas/New Year holiday period.
October 2025 Update - Retaining wall footing complete. Road shoulder construction in progress.
September 2025 Update - Stage 1 works have commenced. Tree clearing in progress.
September 2025 Update - Stage 1 works to commence next week.
August 2025 Update - The construction tender has been awarded. Pre works documentation is being prepared by the Contractor. Stage 1 to commence around mid-September 2025.
July 2025 Update - The construction tender submissions have been received and are being evaluated. Council anticipates a site establishment date for Stage 1 towards the end of August. The watermain relocation works have commenced.
June 2025 Update - The construction tender is currently live, and submissions are due on 04 July 2025. Council anticipates a site establishment date for Stage 1 towards the end of August and is aiming to have the watermain relocation done prior to this.
Dolphin Point Road , Dolphin Point 2539