11/11/2024 - Works are progressing well on the Basin Walk, and on schedule for completion by the end of November 2024.
- 4 of 7 new passing bays are completed
- 8 of 11 sections of new boardwalk are completed
- stairs opposite Milsons Ln are completed and open to the public
- new clips have been installed at the Larmer Ave section
Basin Walk Upgrade is on track for late November 2024 completion.
20/9/2024 - Gravel Footpath: Stage 1, between Loralyn Av and Frederick St, is complete. Works continue between Frederick St and Paradise Beach Rd. Expected completion end of November. All track entries are closed.
Boardwalk Track: Installation of stainless-steel posts has begun. Eastern entrance boardwalk at Ray Brookes Reserve, will be extended 120m over muddy section. Completion planned for end of November. All track entries are closed.
3/9/2024 - Gravel Footpath: The gravel footpath upgrade works, parallel to Loralyn Avenue, are planned to start early September 2024 and will be carried out by Councils' Basin District.
Boardwalk Track: The boardwalk and track upgrade works, parallel to Greville Avenue, start 9 September ongoing to November 2024 and will be carried out by Basco Projects. Updates will be posted here. Subscribe for updates.