- Project StatusConstruction
- Last reviewed
20 April 2023
About the project
In April 2021 Council received grant funding of $5.3 Million under the NSW Government’s Restart NSW Infrastructure Grant.
The $5.3 Million together with $1.63 Million of Council funding and an $80,000 in-kind contribution from the Ulladulla Local Aboriginal Land Council (ULALC) will see the following projects undertaken within the next three years:
Progress to date includes:
1. Plantation Point - Completed
2. Palm Beach/Sanctuary Point – Completed
3. St Georges Basin/Sanctuary Point – Basin Walk
- Stage 1 - Shared User Path, Sanctuary Point Road – The path has been well used and is almost complete. The construction of the 3rd pedestrian bridge near Isons will be completed in May 2023. The construction of the concrete path connections will follow.
- Stage 2 - Basin Walk. This project was completed in February 2022 however shortly after practical completion the walk was subject to the two major storm events in March and July. An Insurance claim was received for the missing sections of boardwalk and most of the works have been undertaken by the contractor to rectify these sections. Council is seeking additional funding/grants to remediate the affected gravel sections of the path.
4. Sanctuary Point - Bherwerre Wetlands
GC Civil Contracting Pty Ltd has been awarded Stage 1 works which include works on the northern side of the canal including:
- Carpark, including 2 accessible car spaces off The Park Drive
- 393m of 2m wide accessible boardwalk
- 420m of 1.2m boardwalk from Larmer Avenue
- Viewing Platform at the junction of the canal and Cockrow Creek
- Seats
- Interpretive signage.
Construction will commence in May 2023 and is expected to be completed by July 2023.
For an overview of this project please refer to the Bherwerre Wetland Concept Plan D4 and the web project page.
5. Hyams Beach – upgrade to existing amenities, improved pedestrian access, upgrade of BBQ’s picnic shelters and beach access. For an overview of this project, visit the Hyams Beach Master Plan web page.
6. Ulladulla Headland and Warden Head Walking Trails
- North – Remediation of the existing One Walk for All track – Contract has awarded and the Contractor – Vogue Landscapes will commence works late May 2023.
- South – The tender is currently being prepared for the Coomee Nulunga Cultural Walk and includes construction of boardwalks and gravel paths, improvements to viewing areas and signage, and the installation of the Bunaan Sculpture commissioned by the Ulladulla Local Aboriginal Land Council (ULALC).
7. Murramarang Coastal Walk Extension
The new Murramarang Coastal Walk is a multi-day walking track that traverses some of the Australia's most stunning coastlines within existing National Parks and Wildlife Service areas. The aim of the tourism project was to extend this walk from Bawley Point to Narrawallee on Council owned and managed parcels of land. However, the Murramarang Walk by NPWS now starts/commences from Pretty Beach
This project will be titled ‘Southern Headlands Walk’ from Narrawallee Headland to Blackburn Headland and will traverse and incorporate existing walks along the route. The walk will be extended to Bawley Point pending future funding opportunities.
Scope of works planned will include:
- Range of directional and interpretative signage, bollards and identification plaques
- Track upgrades on norther section of Blackburn Head
These projects are proudly supported by the NSW Government.