- Project StatusIn Progress
- Where
Murramarang Road, Bawley Point 2539
- Estimated completion date19 December 2025
One lane
Reduced speed
- Last reviewed
20 November 2025
The latest
20/11/2025 - The bridge remains on track for completion and opening around 19 December 2025. Contractor, Jirgens Civil, has advised that works are expected to commence 23rd November 2025. The path to Kioloa is now complete with some missing sections awaiting NBN pits to be raised.
About the project
Section 3 - Shelly Beach Access Carpark to O’Brien St Intersection
Council has gained NSW Government funding to complete this section of path as part of the election commitment to support active transport in the Shoalhaven region.
Construction is in progress and expected to be complete by September 2025.



History
- 16/10/2025 - Approximately 65% of the concrete path has now been constructed. Preparation works for the pedestrian bridge are scheduled to commence in early November 2025, with the bridge expected to be open to the public by mid-December.
- 18/08/2025 - Construction has been moving along despite the recent wet weather events. Approximately 460 lm of concrete path has been poured. The project is approximately 40% complete.
- July Update 2025 - Footpath works continuing.
- June 2025 Update - Works continuing from the Shelly Beach carpark end.
- May 2025 Update - Works have commenced from the Shelly Beach carpark end.
- May 2025 Update - Works to commence on 05/05/2025, weather permitting. Refer to the notice of commencement for further details.
- April 2025 Update - The contract has been awarded. Preliminaries and pre works documentation are in progress. Site commencement date will be confirmed soon.
- March 2025 Update - The contract has been awarded. Preliminaries and pre works documentation is in progress.
- January 2025 Update - Tender evaluation in progress.
- December 2024 Update - Tender evaluation in progress.
- November 2024 Update - Tender submissions due in Thursday 5 December 2024.
- October 2024 Update - Project to be tendered in November 2024.
- September 2024 Update - Finalisation of design continuing. Expect to tender this section of the path late October 2024.
- July 2024 Update - Finalisation of design continuing.
- June 2024 Update - Finalisation of the design has commenced with additional survey carried out for the shorter community chosen route at the Kioloa end.