Moss Vale Road Urban Release Area - Water Infrastructure

The Moss Vale Road Urban Release Area (URA) is a regionally significant residential development located between Bomaderry and Cambewarra village.

The new water pumping station as viewed from the street.

The latest

All work packages have now been completed and works operational.

About the project

The current projected development yield is 3,400 residential lots. In order to supply adequate future servicing to the Urban Release Area (URA), Shoalhaven Water progressed detailed designs for the water and wastewater infrastructure, with construction of the works completed March 2025

Progress so far

  • Project approval – 2020
  • Award of design consultants – 2020
  • Package 1: Water Main Lead-in Works placed in operation December 2021
  • Overall water detailed design completion – 2022
  • Package 2: Illaroo Road Water Pumping Station Upgrades placed in operation April 2024
  • Package 3: Construction of new rising mains placed in operation March 2025
  • Package 4: New 3.5ML Water Reservoir placed in operation July 2024

About the packages of works

Package 1 - Stage 1 water main lead-in work

Package 1 involved the extension of the existing Cambewarra water main network along Main Road and Moss Vale Road, to the Moss Vale Road URA.

Progress so far

  • Package 1 works completed in 2021.

Package 2: Illaroo Road water pumping station upgrade

Package 2 involved the construction of a new upgraded water pumping station.

Progress so far

  • Package 2 works were placed in operation April 2024.

Package 3: Construction of New Rising Mains

Package 3 involves constructing new rising mains to connect the Cambewarra, Badagarang, and Bomaderry water networks.

Progress so far

  • Package 3 works were placed in operation march 2025.

Package 4: New water reservoir

Package 4 involved the construction of a new 3.5ML water reservoir on the existing Cambewarra Reservoir Site at Reservoir Lane.

Progress so far

  • Package 4 works were placed into operation July 2024.

If you have any questions about the above works, please contact Project Manager Robert Greig via email at robert.greig@shoalhaven.nsw.gov.au.

For more information, including the detailed stages, visit the Planning for Growth in Nowra - Bomaderry Get Involved web page.