18/4/2024 - Announcement: Kangaroo Valley Road is now open and under traffic control, with one lane open to motorists. The road was closed 4pm Saturday 6 April after severe rainfall threatened the stability of a section of road as well as 2 new landslip damages. Motorists using Kangaroo Valley Road are advised to allow an extra 5 – 10 minutes when travelling. 12-tonne load limit. Find more details under - About the works.
12/3/2024 - Announcement: Contraflow traffic conditions ongoing. All remaining landslip repair works are planned to be completed under contraflow traffic conditions. Guardrail (crash barrier) installation is planned for March 2024. Find details under - About the works. Subscribe to this page for updates.
27/2/2024 - Announcement: Rescheduled completion of landslip repair works at Site 2 is Monday 26 February 2024, weather permitting. The latest: Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'.
20/2/2024 - Announcement: Planned completion of works at Site 2 is 16 February 2024, weather permitting. Intermittent full road closures at Site 2 near rural address 1167 between 9am and 1.30pm 15 February and 16 February 2024. Expect 30min delays. Otherwise, single lane contraflow traffic conditions. No pedestrian access.
2/1/7/2024 to 23/2/2024 – Updated three-week Lookahead program released each week by contractor, Symal, and published weekly on this page under ‘Related Documents’. Repair works and road closures detailed weekly for all sites under ‘About the works’.