17/4/2024 - Announcement: Road will be open Anzac Day Thursday 25 April 2024. Weekend openings resume Saturday 20 and Sunday 21 April 2024. Due to 7 April 2024 natural disaster (AGRN1119) storm event full road closures at Site 5 rural address 394, traffic restricted to resident access only and 3-tonne load limit. As restrictions will be reviewed and monitored daily, please subscribe to this page for updates.
10/4/2024 - Temporary Closure: Following the recent 7 April 2024 natural disaster (AGRN1119) storm event full road closures are in place at Site 5 rural address 394 and traffic is restricted to resident access only with a 3-tonne load limit. As restrictions will be reviewed and monitored daily in relation to the progress of repairs and weather conditions, please subscribe to this page for updates.
3/4/2024 - Temporary Closure: Planned closures. At Site 5 - rural address 394, planned full road closures are ongoing to Wednesday 15 May due to groundwater issues slowing works. At Site 2, 3 and 4 planned full road closures in place for 1 week from Thursday 16 May to 22 May, weather permitting. Find details under - About the works.
26/3/2024 - Announcement: Road open Easter weekend. From Good Friday 29 March to Easter Monday 1 April 2024, Bunkers Hill Road will be open and repair works will be shut down. Repair works resume Tuesday 2 April 2024. Council appreciates your patience and extends good will for a safe Easter weekend.
12/3/2024 - Temporary Closure: Planned road closures at Site 5 rural address 394 Monday to Saturday 7am to 4pm, are ongoing to 1 May 2024. Site 5 load limit increased to 9-tonne. Due to the structural aspects of repairs progressing, the load limit is increased to 9-tonne in favourable weather conditions. This may change, depending on rainfall and observations on site as works progress. Subscribe to this page for updates.
27/2/2024 - Announcement: Load limits are lifted at Site 2, 3 and 4. Upcoming road closures are planned from Thursday 2 May to Wednesday 8 May 2024 at Site 2, 3 and 4 for final pavement and spay sealing works. Load limit of 5-tonne remains in place at Site 5 - near rural address 394. Closures are ongoing at Site 5 - near rural address 394 - to Wednesday 1 May 2024. Find more details below - About the works.
27/2/2024 - Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'.
From 2/1/7/2024 to 23/2/2024 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page weekly under ‘Related Documents’. Repair works and road closures were also detailed weekly for all sites under ‘About the works’.