Penguins Head Road - Culburra Beach - Landslip

Landslip - Embankment damage is scheduled for repair works.

The latest

26/09/2023 - Council will be undertaking further geotechnical investigation works on Monday 9 October 2023 to determine if further remedial works are required. Public access to Tilbury Reserve may be restricted for a short duration.

About the works

2023 Works history

  • 16/02/23 - Temporary remediation works have been completed.

2022 Works history

  • 22/12/2022 - Temporary landslip remediation works completed. Additional drainage works to be undertaken early February 2023.
  • 19/12/2022 - Temporary reconstruction works commenced Monday 19th December on the access road. The area will be closed to the public. Repairs to the access road are to be completed by Friday 23rd December with remaining works undertaken later in January.
  • 12/12/2022 - Design for temporary reconstruction work is complete. Works are scheduled to begin by 16th December 2022. There will be no access during construction.

  • 20/11/2022 - Geotechnical engineer investigation has been completed. Solution report for design is complete and ready for review by council.