Gerroa Road - Coolangatta - Pavement Repair

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 following an East Coast Low and rain events. This had a major impact on our communities, with landslips affecting roads and property. Gerroa Road, Coolangatta, was impacted by these rain events resulting in planned repair works.

The latest

28/03/2024 - Surface defects are scheduled to be undertaken later in April 2024. This will involve the removal of the wearing course and re-application. Line marking will be scheduled for mid-May 2024.

Select image below for a closer look at pavement.

About the works

gerrroa rd 1.JPG  Pavement damage along Gerroa Road that has been patched.

2024 Works history

20/03/2024 - Surface defects are scheduled to be undertaken after the Easter Long weekend 2024. This will involve the removal of the wearing course and re-application. Line marking will be scheduled for mid-late April 2024.
28/02/2024 - The last update for this project is still current. Further updates will be provided as new information becomes available.
1/02/2024 - Pavement repair works are currently being carried out with an expected completion date mid-February 2024. Please expect changes to traffic conditions and possible delays.

 

2023 Works history

21/12/2023 - A contract to undertake pavement repairs has been awarded. Works are scheduled to commence mid January 2024. Please expect changes to traffic conditions and possible delays.

07/12/2023 - Pavement repair works have been tendered for construction. Following the Tender process, works are expected to commence early in the new year.

01/11/2023 - Pavement repair works are being tendered for construction in the coming weeks. Following the tender process, works are expected to commence early 2024.

08/09/2023 - Transport NSW has approved the repair methodology, and pavement works are currently being scheduled to be carried out mid November 2023.

18/08/2023 - Council has submitted a scope and cost estimate to repair the damaged section of the road to TfNSW for approval. Works will be carried out following TfNSW approval.

21/07/2023 - The last update for this project is still current. Further updates will be provided as new information becomes available.

06/04/2023 - A quotation for ground investigations and pavement designs has been issued. Once complete, pavement designs will be submitted to Transport NSW for scope of work and funding approval.

23/03/2023 - A quotation for ground investigations and pavement designs will be issued in April 2023 prior to submitting to Transport NSW for scope of work and funding approval.

02/02/2023 - A Geotechnical Engineer will be engaged in February 2023 to carry out pavement investigation works.

2022 Works history

12/12/2022 - Tender expected in March 2023 following sampling and testing investigations. 

A Northern District Pavement Repair Program, including sections of Gerroa Road, is expected to be put to tender in March 2023 following geotechnical investigations. In the interim please drive slowly with caution.