Coolangatta Road - Coolangatta - Pavement Repair

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 following an East Coast Low and rain events. This had a major impact on our communities, causing rapid deterioration to pavements and roads. Coolangatta Road, Coolangatta, was severely impacted by the March East Coast Low and rain events.

The latest

02/04/2024 - The last update is still current for this project. Further updates will be posted as new information becomes available.
20/03/2024 - Line marking is scheduled to be undertaken in mid-late April 2024 in conjunction with Gerroa Road works.

Select image below for a closer look at repair works in progress.

About the works

Coolangatta Rd 1.JPG Coolangatta Rd.JPG

2024 Works history

20/03/2024 - Linemarking is scheduled to be undertaken in mid-late April 2024 in conjunction with Gerroa Rd works.
28/02/2024 - The last update for this project is still current. Further updates will be provided as new information becomes available.
1/02/2024 - Pavment repair works have been completed. Linemarking of the new works will be carried out in the coming weeks.

 

2023 Works History

21/12/2023 - A contract to undertake pavement repairs has been awarded. Works are scheduled to commence mid-late January 2024. Please expect changes to traffic conditions and possible delays.

01/11/2023 - Pavement repair works have been tendered for construction. Following the tender process, works are expected to commence early 2024.

18/08/2023 -Transport NSW have approved the repair methodology for the pavement reconstruction works.

25/05/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.

06/04/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.

28/03/2023 - Northern Maintenance Roads Crew are undertaken pothole repairs on Coolangatta Road this week Tuesday 28 March to Friday 31 March, weather permitting. Traffic control is in place so please plan for delays.

23/03/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.

19/01/2023 - Council has submitted request to Transport NSW to approve the repair method before works can be tendered for Construction.

19/01/2023 - Geotechnical Investigations for pavement repairs have been carried out to inform appropriate repair methods. Council is currently waiting for Transport NSW to approve the repair method before works can be Tendered for Construction. A temporary 60km/h speed zone and pothole warning signs have been installed to inform motorists of the condition of the road. 

 

2022 Works History

23/12/2022 - Tender expected in January 2023 following sampling and testing investigations.

28/11/2022 - Geotechnical Investigations for pavement repairs are being carried out to inform appropriate repair methods prior to tendering the works in January 2023. A temporary 60km/h speed zone and pothole warning signs have been installed to inform motorists of the condition of the road.