The Wool Road / Mernie Street, Old Erowal Bay - Pavement Damage

Following completion of the new channelised right turn at the intersection of The Wool Road and Mernie Street, Council has identified pavement requiring rectification. Council's contractor will be undertaking these works.

The latest

07/06/2023 - Pavement rectification works have been delayed and will now commence in mid June 2023 with expected completion in late June 2023. During this time the site will be under traffic light control with lane closure on The Wool Road at the intersection with Mernie Street. Access to Mernie Street via The Wool Road will be restricted to residents only.

About the works

  • 26/05/2023 - Pavement rectification works will commence in early June 2023 with expected completion in late June 2023.   During this time the site will be under traffic light control with lane closure on The Wool Road at the intersection with Mernie Street.  Access to Mernie Street via The Wool Road will be restricted to residents only.

  • 12/05/2023 - Pavement rectification works to be undertaken late May 2023.   During this time the site will be under traffic light control with lane closure on The Wool Road at the intersection with Mernie Street.  Access to Mernie Street via The Wool Road will be restricted to residents only.

  • 27/04/2023 - From 5 May to 12 May 2023 the contractor will be undertaking pavement rectification.  Speed reduction and closure of one lane on The Wool Road will occur for the duration of the works.

  • Project is complete, pending rectification of asphalt defects. Rectification works will be on-going for several weeks.