The Shoalhaven was declared a Natural Disaster Area after the March 2022 East Coast Low and subsequent rain events caused extensive damage to many Council assets. Sussex Inlet Road was severely impacted and extensive road repair works are required.

The latest

05/03/2024 - Pavement repair works are scheduled by the contractor to commence early April 2024. Works are expected to take 2 weeks to complete, weather permitting.

About the works

Sussex Inlet Rd.JPG

2024 Works history

  • 29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.

 

 

2023 Works history

  • 15/11/2023 - Tender is expected to be awarded in December 2023 with works commencing in early 2024.

  • 27/07/2023 - Project scope and estimate have been updated to reflect TfNSW requirements. Works are being incorporated into a large contract addressing pavement remediation for five main roads in the Southern District. Tenders are expected to be advertised by the end of July with works to commence later this year, dependent on Council’s consideration and contractor availability.

  • 24/05/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval.

  • 06/04/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval.

  • 24/03/2023 - Ground investigations are underway. Pavement designs will be submitted to TfNSW for approval in April 2023.

  • 02/02/2023 - Field work for sampling and testing of the pavement is currently being carried out.

  • 18/01/2023 - Tender expected in February 2023 following sampling and testing investigations in late January early February 2023.

  • 10/01/2023 - A geotechnical consultant has been engaged to commence sampling and testing works to inform the repair method. Field work will be carried out late Jan/early Feb 2023. Following geotechnical investigations and approval of the scope of work, works will be Tendered for construction. In the interim please drive slowly with caution.

2022 Works history

  • 19/12/2022 - A Southern District Pavement Repair Program, including sections of Sussex Inlet Road, is expected to be put to tender in February 2023 following sampling and testing investigations. In the interim please drive slowly with caution. Temporary works in November have seen the road 'jet-patched' to fill potholes complete.

  • 12/12/2022 - A Southern District Pavement Repair Program, including sections of Sussex Inlet Road, is expected to be put to tender in February 2023 following geotechnical investigations. In the interim please drive slowly with caution. Temporary works in November have seen the road 'jet-patched' to fill potholes complete.

  • 01/12/2022 - Road rehabilitation works will be completed along several sections of Sussex Inlet Road in early 2023. Temporary works in November have seen the road 'jet-patched' to fill potholes as an interim.

  • 01/11/2022 - A Southern District Pavement Repair Program, including Sussex Inlet Road, is expected to put to tender in December 2022. Road rehabilitation works will be completed along several sections of Sussex Inlet Road commencing early next year.