Northern District - Bushfire Cleanup Works
Announcement
Abernethy’s Rd – to commence mid-November progress, to be completed by end of October
• Hughes Rd – on hold pending dry weather
• Jacks Corner Rd – in progress, to be completed mid-November
• Lower Bugong Road – to commence in early November
• Selby’s Road – in progress, to be completed by end of October
Work Involves the cleanup of fallen and dangerous trees from road verges throughout the Shoalhaven LGA as a consequence of the 2019/2020 bushfires.
A total of 75 roads with a total distance of 271kms will be cleaned up in the Shoalhaven LGA. Work is funded by the national Disaster Recovery Funding Arrangements.
- Public access
Open
During daylight hours
- Last reviewed
26 October 2022
About the works
Latest update
Roads - October:
- Bolong Road - in progress, to be completed by end of October
- Selby’s Road – in progress, to be completed by end of October
- Tallowa Dam Rd (stage 2) Rd – in progress, to be completed by end of October
- Jacks Corner Road - in progress, to be completed by November
Roads listed for commence November:
- Albernathy's Road - to commence in November
- Lower Bugong Road - to commence in early November
- Hughes Road - on hold pending dry weather
Roads Completed:
- Radiata Place
- Duffys Lane / Bugong Firetrail
- Tallowa Dam Road (Stage 1)
- Mt Scanzi Road
- Illaroo Road
- Riversdale Road
- Bundanon Road