Main Road - Cambewarra Village - Pavement Repair

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and subsequent rain events. This had a major impact on our communities, causing rapid deterioration to pavements and roads. Main Road, Cambewarra Village, was severely impacted by these rain events resulting in planned repair works.

The latest

12/02/2024 - Pavement repair works on Main Road, Cambewarra have been completed.

About the works

Before Photo - Pavement damage on Main Road         After - Main Road repairs

2024 Works History

29/01/2024 - Asphalt patch repair works will be carried out on Main Road, Cambewarra on Thursday 1 February and Friday 2 February 2024. This will take place between Moss Vale Road and Good Dog Creek.

 

2023 Works history

12/10/2023 - Council has submitted a scope of works to Transport for NSW for approval to repair the damaged pavement on Main Road.

08/09/2023 - Pavement repairs are to be scoped prior to submitting to Transport NSW for funding approval.

06/04/2023 - A quotation for ground investigations and pavement designs has been issued. Once complete, pavement designs will be submitted to Transport NSW for scope of work and funding approval.

02/02/2023 - A Geotechnical Engineer will be engaged in February 2023 to carry out pavement investigation works. A Northern District Pavement Repair Program, including sections of Main Road, will be put to Tender following geotechnical investigations and approval of works by Transport NSW. In the interim please drive slowly with caution.

 

2022 Works history

19/01/2022 - Expected to be put to tender in March 2023 following sampling and testing investigations.

19/01/2022 - A Northern District Pavement Repair Program, including sections of Main Road, is expected to be put to tender in March 2023 following sampling and testing investigations. In the interim please drive slowly with caution.

08/12/2022 - Sampling and testing to determine an appropriate is scheduled.

7/12/2022 - Sampling and testing to determine an appropriate reconstruction method is in progress and once complete will allow for a tendering process to commence. At this stage it is expected that the tendering process will commence during the month of March 2023. In the interim the Northern District Office will be undertaking short term maintenance activities to provide for the longer term reconstruction work.  The next update will occur when the tendering process is approaching.

The tender package will form part of the Northern District Round 2 package which also plans to include; 

  • Kangaroo Valley Road, Berry Mountain
  • Hillandale Road, Broughton Vale       
  • Agars Lane, Berry
  • Main Road, Cambewarra 

 

21/11/2022 - A Northern District Pavement Repair Program, including sections of Main Road, is expected to be put to tender in March 2023 following geotechnical investigations. In the interim please drive slowly with caution.

31/10/2022 - A tender to deliver a Northern District Pavement Repair Program, including sections of Main Road is expected to be called in December 2022. Road repair works are expected to commence in the new year.