Jindy Andy Lane - Pyree Numbaa - Pavement Repair

Pavement repair

The latest

All works under the external tender package have been completed.

About the works

  • 31/10/2022 - A contractor has been engaged to reinstate the line marking that was removed during pavement repairs. Works are scheduled for mid-November, weather permitting.
  • 22/10/2022 - A request for quote has been sent to suitable line marking contractors. Quotes are expected to be received by 28th October, with works to be undertaken in November.
  • 10/09/2022 - Pavement works under the external tender package have been completed. Line marking remains outstanding.
  • 08/09/2022 - Asphalt pavement repair work on Jindy Andy Lane was completed on schedule this week.
  • 01/09/2022 - Asphalt repair work commenced Thursday 01/09/22 and will continue during the week weather permitting. A single lane will operate under traffic control during this time. Council advises that residents should allow for extra travel time.
  • 22/08/2022 - Contractors due to commence Tuesday 23rd August weather permitting. Central AC program scheduled for 4-week construction period.