Jacks Corner Road - Kangaroo Valley - Sealed Pavement Repair

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and subsequent rain events. This had a major impact on our communities, causing rapid deterioration to pavements and roads. Jacks Corner Road, Kangaroo Valley, was impacted by these rain events resulting in planned repair works.

The latest

22/11/2023 - Pavement repair works on Jacks Corner Road are now complete.

About the works

2023 Works history

Jacks-Cnr-Rd-Under-Construction.png

01/11/2023 - Pavement repair works on Jacks Corner Road are in progress and are expected to be completed late November, weather conditions permitting.

31/08/2023 - Transport NSW has approved the repair methodology, and pavement works are currently being scheduled to be carried out in late October 2023.

14/08/2023 - Council has submitted a scope of works and cost estimate for the repairs of the damaged sections of road, to be approved by Transport NSW. Works will be carried out following Transport NSW approval.

23/03/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.

 

2022 Works history

Jacks Cnr Road, damaged road. Jacks Cnr Road, post post from damage filled.

19/12/2022 - Sealed: Sampling and testing Investigations for pavement repairs are being carried out to inform appropriate repair methods, prior to Tendering works in January 2023. Unsealed: Repairs to the unsealed section of Jacks Corner Road have been completed.

12/12/2022 - Grading work along the unsealed section has been completed. Bushfire clean-up works involve overhead pruning by using an elevated work platform. This has commenced and should be completed by 16 December. Work is being undertaken with traffic control.

jacks corner.JPG

29/11/2022 - Grading work along the unsealed section has been completed. Bushfire clean-up works involve overhead pruning by using an elevated work platform. This has commenced and should be completed by 9 December. Work is being undertaken under traffic control.

31/10/2022 - Unsealed: Bushfire clean-up works using heavy machinery for tree removal has been completed. This will allow road grading work along the unsealed section to commence the week starting 31 October. When road grading work is completed in approximately 3 weeks’ time, bushfire cleanup work will resume and will involve overhead pruning utilising an elevated work platform and traffic control.

5/10/2022 - Sealed: Geotechnical Investigations for pavement repairs are being carried out prior to funding approval and delivery of works. Unsealed: Bushfire clean up works are currently underway. Works to repair the unsealed sections of the road will follow these works, likely to commence late November 2022.

01/10/2022 - This road has been scoped for repairs. Geotechnical investigations for pavement repairs are being carried out prior to funding approval and delivery of works. Local civil contractors are likely to be awarded the repair works on basis of size and location.jacks corner 1.JPG