Cabbage Tree Lane - Nowra Hill - Pavement Repair

Pavement repair

The latest

All works under the external tender package have been completed.

About the works

  • 31/10/2022 - A contractor has been engaged to reinstate the line marking that was removed during pavement repairs. Works are scheduled for mid-November, weather permitting.
  • 22/10/2022 - A request for quote has been sent to suitable line marking contractors. Quotes are expected to be received by 28th October, with works to be undertaken in November.
  • 20/09/2022 - Pavement works under the external tender package have been completed. Line marking remains outstanding.
  • 08/09/2022 - Asphalt repair work will continue this week from Tuesday 06/09/2022 to Friday 09/09/2022, weather permitting. A single lane will operate under traffic control during this time. Council advises that residents should allow for extra travel time.
  • 20/08/2022 - Contractors due to commence Tuesday 23rd August. Central AC program scheduled for a 4-week construction period.