04/04/2024 - Project complete with only minor works remaining.
06/03/2024 - Jetty deck installation continuing. Pontoon install to occur next week. Shared User Path construction in progress.
20/02/2024 - Piling works are nearing completion. Jetty construction and shared user path construction to occur concurrently from next week.
18/01/2024 - Site to be established mid next week for works to begin on the 29th January following the long weekend.
December 2024 - The construction contract has been awarded. Construction to commence on site mid-to-late January 2024.
November 2023 Update - The preferred tenderer for the works has been selected. Due to budget constraints only Stage 1 will be constructed. Council is aiming to award the contract by mid-November with construction to start late January 2024.
September 2023 Update - Tenders have been received and are being evaluated.
August 2023 Update - The construction contract is currently being tendered.